Below is a listing of the Revisions and Changes made to UFGS Sections for each release. You can narrow the list by selecting a UFGS Release date from the drop-down and clicking 'Apply'.
| KEY | PREPARING ACTIVITY (PA) | A Army | N Navy | F Air Force | S NASA [ARCHIVED] |
|---|---|---|---|---|---|
| ACTION | N New | R Revision | C Change | D Deletion |
| Release | PA | UFGS Section | Date | Action | Change # | Nature of Change or Revision |
|---|---|---|---|---|---|---|
| Aug-2010 | N | UFGS 09 29 00 Gypsum Board | Aug-2010 | R | Added GEI or SCS certification and other minor revisions; revised subpart 3.4 | |
| Aug-2010 | A | UFGS 09 30 00 Ceramic Tile, Quarry Tile, and Paver Tile | Aug-2010 | R | Added GEI or SCS certification | |
| Aug-2010 | A | UFGS 09 35 16 Chemical-Resistant Quarry Tiling | Aug-2010 | R | Added GEI or SCS certification | |
| Aug-2010 | A | UFGS 09 51 00 Acoustical Ceilings | Aug-2010 | R | Added GEI or SCS certification; CCRs 3579 and 3580; Revised system | |
| Aug-2010 | N | UFGS 09 64 00 Portable (Demountable) Wood Flooring | Aug-2010 | R | Added GEI or SCS certification | |
| Aug-2010 | A | UFGS 09 64 23 Wood Parquet Flooring | Aug-2010 | R | Added GEI or SCS certification | |
| Aug-2010 | A | UFGS 09 64 29 Wood Strip and Plank Flooring | Aug-2010 | R | Added GEI or SCS certification | |
| Aug-2010 | N | UFGS 09 64 66 Wood Athletic Flooring | Aug-2010 | R | Added GEI or SCS certification | |
| Aug-2010 | A | UFGS 09 65 00 Resilient Flooring | Aug-2010 | R | Added GEI or SCS certification | |
| Aug-2010 | A | UFGS 09 65 33 Conductive Vinyl Flooring | Aug-2010 | R | Added GEI or SCS certification | |
| Aug-2010 | A | UFGS 09 65 66 Resilient Athletic Flooring | Aug-2010 | R | Added GEI or SCS certification | |
| Aug-2010 | A | UFGS 09 66 13 Portland Cement Terrazzo Flooring | Aug-2010 | R | Added GEI or SCS certification | |
| Aug-2010 | A | UFGS 09 66 16 Terrazzo Floor Tile | Aug-2010 | R | Added GEI or SCS certification | |
| Aug-2010 | A | UFGS 09 66 23 Resinous Matrix Terrazzo Flooring | Aug-2010 | R | Added GEI or SCS certification | |
| Aug-2010 | S | UFGS 09 67 23.13 Standard Resinous Flooring | Aug-2010 | R | Revised General Note, subparts 1.4, 3.2.1.1, 3.2.1.2 and 3.2.2; submittal article configuration compliance; added subparts 1.3, 1.3.1, 1.3.2,1.5, 3.3.1 and 3.6 | |
| Aug-2010 | A | UFGS 09 67 23.14 Chemical Resistant Resinous Flooring | Aug-2010 | R | Added GEI or SCS certification | |
| Aug-2010 | N | UFGS 09 67 23.15 Fuel Resistive Resinous Flooring, 3-Coat System | Aug-2010 | R | Revised Tennant Topcoat info in Table II | |
| Aug-2010 | N | UFGS 09 67 23.16 Fuel Resistive Resinous Flooring, 5-Coat System | Aug-2010 | R | Revised Tennant Topcoat info in Table II | |
| Aug-2010 | A | UFGS 09 69 13 Rigid Grid Access Flooring | Aug-2010 | R | Updated criteria for applying loads allowed, deflection and size of panels to coincide with industry | |
| Aug-2010 | A | UFGS 09 69 19 Stringerless Access Flooring | Aug-2010 | R | Updated criteria for applying loads allowed, deflection and size of panels to coincide with industry | |
| Aug-2010 | A | UFGS 09 72 00 Wallcoverings | Aug-2010 | R | Added GEI or SCS certification | |
| Aug-2010 | A | UFGS 09 83 13 Acoustical Wall Coating | Aug-2010 | R | Added GEI or SCS certification | |
| Aug-2010 | N | UFGS 09 90 00 Paints and Coatings | Aug-2010 | R | Added GEI or SCS certification and other minor revisions | |
| Aug-2010 | N | UFGS 10 22 13 Wire Mesh Partitions | Aug-2010 | R | Added GEI or SCS certification | |
| Aug-2010 | A | UFGS 10 22 19 Demountable and Moveable Partitions | Aug-2010 | R | Added GEI or SCS certification | |
| Aug-2010 | N | UFGS 10 22 26.13 Accordion Folding Partitions | Aug-2010 | R | Added GEI or SCS certification | |
| Aug-2010 | N | UFGS 10 22 26.23 Coiling Partitions | Aug-2010 | R | Added GEI or SCS certification | |
| Aug-2010 | A | UFGS 10 22 26.33 Folding Panel Partitions | Aug-2010 | R | Added GEI or SCS certification | |
| Aug-2010 | A | UFGS 10 22 26.43 Sliding Partitions | Aug-2010 | R | Added GEI or SCS certification | |
| Aug-2010 | A | UFGS 10 26 13 Wall and Corner Guards | Aug-2010 | R | Added GEI or SCS certification | |
| Aug-2010 | A | UFGS 12 21 00 Window Blinds | Aug-2010 | R | Added GEI or SCS certification | |
| Aug-2010 | N | UFGS 12 22 00 Curtains and Drapes | Aug-2010 | R | Added GEI or SCS certification | |
| Aug-2010 | A | UFGS 12 24 13 Roller Window Shades | Aug-2010 | R | Added GEI or SCS certification | |
| Aug-2010 | A | UFGS 12 35 20 Foodservice Casework, Countertops, and Accessories | Aug-2010 | R | Added GEI or SCS certification | |
| Aug-2010 | A | UFGS 12 35 70 Healthcare Casework | Aug-2010 | R | Added GEI or SCS certification | |
| Aug-2010 | A | UFGS 14 24 00 Hydraulic Elevators | Aug-2010 | R | Total revision of 2.4 ELEVATOR DRIVE SYSTEM and 2.5 CONTROL EQUIPMENT | |
| Aug-2010 | S | UFGS 21 13 00.00 40 Fire-Suppression Sprinkler Systems | Aug-2010 | R | Standard tailoring for RCBEA incorporated; other minor revisions throughout | |
| Aug-2010 | S | UFGS 21 13 26.00 40 Deluge Fire-Suppression Sprinkler Systems | Aug-2010 | R | Standard tailoring for RCBEA incorporated; other minor revisions throughout | |
| Aug-2010 | S | UFGS 21 21 00.00 40 Carbon-Dioxide Fire Extinguishing Systems | Aug-2010 | R | Added note and text in subpart 3.2.2; submittal article configuration compliance; other minor revisions throughout | |
| Aug-2010 | N | UFGS 22 00 00 Plumbing, General Purpose | Aug-2010 | R | Revised subpart 2.1 | |
| Aug-2010 | S | UFGS 22 05 83.63 Cured-In-Place Pipe (CIPP) Lining for Plumbing Applications | Aug-2010 | N | New section | |
| Aug-2010 | S | UFGS 22 14 29 Sump Pumps | Aug-2010 | R | Standard tailoring for RCBEA incorporated; other minor revisions throughout | |
| Aug-2010 | S | UFGS 22 15 09 General Service Compressed-Air Systems Cleaning Procedures | Aug-2010 | R | Standard tailoring for RCBEA incorporated; other minor revisions throughout | |
| Aug-2010 | S | UFGS 22 15 14 General Service Compressed-Air Systems, Low Pressure | Aug-2010 | R | Standard tailoring for RCBEA incorporated; other minor revisions throughout | |
| Aug-2010 | S | UFGS 22 66 53 Laboratory Chemical-Waste and Vent Piping | Aug-2010 | R | Standard tailoring for RCBEA incorporated; other minor revisions throughout | |
| Aug-2010 | A | UFGS 23 00 00 Air Supply, Distribution, Ventilation, and Exhaust Systems | Aug-2010 | R | Added GEI or SCS certification; allow flexible elastomeric duct liner | |
| Aug-2010 | S | UFGS 23 01 30.41 HVAC System Cleaning | Aug-2010 | N | New section | |
| Aug-2010 | N | UFGS 23 03 00.00 20 Basic Mechanical Materials and Methods | Aug-2010 | R | Added GEI or SCS certification | |
| Aug-2010 | A | UFGS 23 07 00 Thermal Insulation for Mechanical Systems | Aug-2010 | R | Added GEI or SCS certification; CCR 3250 | |
| Aug-2010 | S | UFGS 23 09 33.00 40 Electric and Electronic Control System for HVAC | Aug-2010 | R | Standard tailoring for RCBEA incorporated; other minor revisions throughout | |
| Aug-2010 | S | UFGS 23 73 13 Modular Indoor Central-Station Air-Handling Units | Aug-2010 | R | Revised General Note, deleted 1.2; submittal article compliance; Added subparts 1.3. 1.3.1, 1.3.2, 1.4, 1.5, 2.1and 3.8; other minor revisions throughout | |
| Aug-2010 | S | UFGS 23 82 16 Air Coils | Aug-2010 | R | Added "Note" below Part 1 General; submittal article compliance; revised subpart 1.3 and 1.4; other minor revisions throughout | |
| Aug-2010 | S | UFGS 23 82 19 Fan Coil Units | Aug-2010 | R | Submittal article compliance; other minor revisions throughout | |
| Aug-2010 | S | UFGS 23 82 43 Electric Duct Heaters | Aug-2010 | R | Submittal article compliance; other minor revisions throughout | |
| Aug-2010 | S | UFGS 26 05 00.00 40 Common Work Results for Electrical | Aug-2010 | R | Standard tailoring for RCBEA incorporated; other minor revisions throughout | |
| Aug-2010 | S | UFGS 26 05 13.00 10 Medium-Voltage Cables | Aug-2010 | R | Standard tailoring for RCBEA incorporated; other minor revisions throughout | |
| Aug-2010 | S | UFGS 26 09 23.00 40 Lighting Control Devices | Aug-2010 | R | Standard tailoring for RCBEA incorporated; other minor revisions throughout | |
| Aug-2010 | S | UFGS 26 12 19.00 40 Pad-Mounted, Liquid-Filled Medium-Voltage Transformers | Aug-2010 | R | Standard tailoring for RCBEA incorporated; other minor revisions throughout | |
| Aug-2010 | S | UFGS 26 18 23.00 40 Medium-Voltage Surge Arresters | Aug-2010 | R | Standard tailoring for RCBEA incorporated; other minor revisions throughout | |
| Aug-2010 | S | UFGS 26 23 00.00 40 Switchboards and Switchgear | Aug-2010 | R | Standard tailoring for RCBEA incorporated; other minor revisions throughout | |
| Aug-2010 | S | UFGS 26 24 16.00 40 Panelboards | Aug-2010 | R | Standard tailoring for RCBEA incorporated; other minor revisions throughout | |
| Aug-2010 | S | UFGS 26 24 19.00 40 Motor-Control Centers | Aug-2010 | R | Standard tailoring for RCBEA incorporated; other minor revisions throughout | |
| Aug-2010 | S | UFGS 26 28 21.00 40 Automatic Transfer Switches | Aug-2010 | R | Standard tailoring for RCBEA incorporated; other minor revisions throughout | |
| Aug-2010 | S | UFGS 26 35 33.00 40 Power Factor Correction Equipment | Aug-2010 | R | Standard tailoring for RCBEA incorporated; other minor revisions throughout | |
| Aug-2010 | S | UFGS 28 05 26.00 40 Grounding and Bonding For Electronic Safety and Security | Aug-2010 | R | Standard tailoring for RCBEA incorporated; other minor revisions throughout | |
| Aug-2010 | S | UFGS 28 31 13.00 40 Fire Detection and Alarm Control, GUI and Logic Systems | Aug-2010 | R | Standard tailoring for RCBEA incorporated; other minor revisions throughout | |
| Aug-2010 | A | UFGS 32 13 11 Concrete Pavement for Airfields and Other Heavy-Duty Pavements | Aug-2010 | R | Title changed to eliminate volume restriction; was Concrete Pavement for Airfields and Other Heavy-Duty Pavements More Than 10000 Cubic Yards | |
| Aug-2010 | N | UFGS 32 13 13.03 Airfields and Heavy-Duty Concrete Pavement Less than 10000 Cubic Yards | Apr-2006 | D | Superseded by UFGS 32 13 11 Concrete Pavement for Airfields and Other Heavy-Duty Pavement Note: The last published PDF version of this Section is available in the previous release in the UFGS Archives. |
|
| Aug-2010 | S | UFGS 32 31 13 Chain Link Fences and Gates | Aug-2010 | R | Submittal article compliance; Added subpart 1.5.2; other minor revisions throughout | |
| Aug-2010 | A | UFGS 33 61 13 Pre-Engineered Underground Heat Distribution System | Aug-2010 | R | Updated poured-in-place insulation requirements | |
| Aug-2010 | S | UFGS 33 77 19.00 40 Medium-Voltage Switch | Aug-2010 | R | Standard tailoring for RCBEA incorporated; other minor revisions throughout | |
| Aug-2010 | S | UFGS 40 17 30.00 40 Welding General Piping | Aug-2010 | R | Submittal article compliance; Added subpart 1.5; revised subpart 3.3.2.1; other minor revisions throughout | |
| Aug-2010 | S | UFGS 40 18 00 Vacuum Systems Process Piping | Aug-2010 | R | Standard tailoring for RCBEA incorporated; other minor revisions throughout | |
| Aug-2010 | S | UFGS 43 41 13.19 Fiberglass Gas Liquid Pressure Vessels | Aug-2008 | D | Section number and title change; Superseded by UFGS 43 41 16.16 Vertical Atmospheric Tanks and Vessels Note: The last published PDF version of this Section is available in the previous release in the UFGS Archives. |
|
| Aug-2010 | S | UFGS 43 41 16.16 Vertical Atmospheric Tanks and Vessels | Apr-2018 | N | Superseding UFGS 43 41 13.19 Fiberglass Gas Liquid Pressure Vessels; submittal article configuration compliance; revised General Note; added subparts 1.2.1.2, 1.2.1.3, 2.3.1, and 3.2; added note to 3.5; other minor revisions throughout | |
| Jun-2010 | S | UFGS 01 33 00 Submittal Procedures | Jun-2010 | R | INTERIM RELEASE: added tailoring for "Construction" in subpart 1.1.1 under SD-01; added tailoring option for "Army" in subpart 1.1.3; other minor revisions in subparts 1.3.5, 1.8, 1.8.1, 1.8.2, and 1.8.3 | |
| Jun-2010 | A | UFGS 22 00 70 Plumbing for Healthcare Facilities | Jun-2010 | R | INTERIM RELEASE: added EPA registration for Copper-Silver Ionization requirement | |
| May-2010 | S | UFGS 01 33 00 Submittal Procedures | May-2010 | R | Revised subpart 1.5.4 and 1.5.9; revised note in 1.8.2 and 1.9; minor revision in article 1.14 | |
| May-2010 | A | UFGS 01 78 00 Closeout Submittals | May-2010 | R | Submittal article configuration compliance and add Navy tailor tags for final cleaning | |
| May-2010 | A | UFGS 02 01 50 Operation, Maintenance and Process Monitoring for Soil Vapor Extraction (SVE) Systems | May-2010 | R | CSI SectionFormat and submittal article configuration compliance | |
| May-2010 | A | UFGS 02 32 00 Subsurface Drilling, Sampling, and Testing | May-2010 | R | CSI SectionFormat and submittal article configuration compliance | |
| May-2010 | A | UFGS 02 35 27 Soil-Bentonite (S-B) Slurry Trench | May-2010 | R | CSI SectionFormat and submittal article configuration compliance | |
| May-2010 | A | UFGS 02 41 00 [Demolition] [and] [Deconstruction] | May-2010 | R | CSI SectionFormat and submittal article configuration compliance | |
| May-2010 | A | UFGS 02 42 91 Removal and Salvage of Historic Construction Materials | May-2010 | R | CSI SectionFormat and submittal article configuration compliance | |
| May-2010 | A | UFGS 02 51 13 Precipitation/Coagulation/Flocculation Water Treatment | May-2010 | R | CSI SectionFormat and submittal article configuration compliance | |
| May-2010 | A | UFGS 02 53 13 Remediation of Contaminated Soils and Sludges by Incineration | May-2010 | R | CSI SectionFormat and submittal article configuration compliance | |
| May-2010 | N | UFGS 03 30 00 Cast-In-Place Concrete | May-2010 | R | Revised para 2.4.8, 2.5.5, 2.8.3; other minor revisions throughout | |
| May-2010 | N | UFGS 05 12 00 Structural Steel | May-2010 | R | Revised para 2.1.2, note in 2.1.2.1, 3.10; other minor revisions throughout | |
| May-2010 | N | UFGS 05 30 00 Steel Decks | May-2010 | R | Revised para 2.3.1, 2.3.1.1 and 3.2.4.1; removed note in 3.2.1; other minor revisions throughout | |
| May-2010 | N | UFGS 05 40 00 Cold-Formed Metal Framing | May-2010 | R | Removed para 3.2.5 and notes in 3.1.1, 3.1.2, 3.1.3; added para 3.1.4; other minor revisions throughout | |
| May-2010 | N | UFGS 05 50 13 Miscellaneous Metal Fabrications | May-2010 | R | Revised note #4 before part 1, para 2.1.7.5 and 2.1.7.6; other minor revisions throughout | |
| May-2010 | N | UFGS 05 51 33 Metal Ladders | May-2010 | R | Revised para 3.3; other minor revisions throughout |
|
| May-2010 | A | UFGS 07 84 00 Firestopping | May-2010 | R | CSI SectionFormat and submittal article configuration compliance | |
| May-2010 | S | UFGS 09 23 82 Fireproof Gypsum Plastering | May-2010 | R | Revised General Note; Submittal article configuration compliance; Added Subpart 1.4 through 1.4.4; other minor revisions throughout | |
| May-2010 | N | UFGS 09 29 00 Gypsum Board | May-2010 | R | Revised para 2.5; other minor revisions throughout | |
| May-2010 | A | UFGS 09 68 00 Carpeting | May-2010 | R | CSI SectionFormat and submittal article configuration compliance | |
| May-2010 | S | UFGS 12 34 00 Manufactured Plastic Casework | May-2010 | R | Submittal article configuration compliance; revised articles 1.4, 1.5, 2.1; other minor revisions throughout | |
| May-2010 | S | UFGS 21 22 00.00 40 Clean Agent Fire Extinguishing Systems | May-2010 | N | New section | |
| May-2010 | S | UFGS 22 07 19 Plumbing Piping Insulation | May-2010 | R | Submittal article configuration compliance; revised 1.5; added subpart 1.6; revised PART 2; other minor revisions throughout | |
| May-2010 | S | UFGS 22 66 53 Laboratory Chemical-Waste and Vent Piping | May-2010 | R | Minor revisions throughout |